KẾ HOẠCH THI CÔNG sân BÓNG đá LA KHÊ CÔNG TY TNHH THƯƠNG mại và xây DỰNG HOÀNG NGUYÊN e

LA KHE FOOTBALL STADIUM CONSTRUCTION PLAN
HOANG NGUYEN TRADING AND SERVICE BUIDING CO.,LTD
I. ABOUT CONSTRUCTION UNIT:
1. GENERAL INFORMATION:
Hoang Nguyen trading & service building Co.,Ltd is professional in sports and civil
works as well as the artificial turf .
Established: September 14, 2001
Address: 16A Le Hong Phong Street, Ward 12, District 10, Ho Chi Minh City
Hanoi Branch is founded in 2007
Address: 95 Chua Boc Street, Dong Da District, Ha Noi
Scope of business:
- Supply and installation of artificial grass football pitches and sports facilities for
Northern market.
- Football field rental service.
Dat Duc sports and football service center were established in 2008
Address: Go Vap district, HCMC
Scope of business:
- Natural grass football field rental services for practicing of national teams, resort,
restaurant, hotel...
11 - People football field were established in Thu Duc district in 2010 with standard of 1
star of FIFA.

Address: 16 Tran Van Nua, Linh Tay Ward, Thu Duc District, Ho Chi Minh City
- Executing successful artificial turf football field for 11 people under 2 stars FIFA
standard which were used to play professionally in the national tournament.
MISSION

Page 1 of 17


“Hoang Nguyen is a leading company in the field of sports development. Our company is
committed to building a comprehensive solution for the artificial turf soccer fields, sports
facilities and residential nationwide with quality guaranteed by advanced technology and
professional execution capabilities”
VISION
“As a pioneer in the construction of the surface of artificial grass football pitches and
sports facilities, we strive for the development of community sports in the country,
committed to our customers and transport best solution to encourage competition”
2. BUSINESS PHILOSOPHY
Our company is focus on works with the following criteria:
- Quality: is one of the company's lodestars in huge and class work.
- Good relationships: warrant maintaining long lasting relationship, and learn to
overcome the customer's wishes.
- Construction progress: ensuring the progress of the work required on time, without
delay.
- Development solution: to build appropriate solutions, and optimal diverse needs of
customers.
3. BUSINESS LICENSES:
Hoang Nguyen trading & service building Co.,Ltd is a unit established under the
investment license of Planning and Investment Department of Ho Chi Minh City with
No. 4102006514 dated on September 14, 2001.
4. OPERATIONS
Constructions:
Civil and industrial, transportation, roads and bridges
Construction of the use of artificial turf and other sports flooring
Construction and installation of equipment for sports facilities and gymnasiums
Local business producing:
Page 2 of 17


Purchasing sports equipment
Trading in building materials, interior decoration, handicraft goods, handicraft goods,


timber, supplies and office machines, stationery, household appliances products, electric
appliances application, electronics, phones and accessories, food, agriculture, forestry and
aquaculture.
Service
Yard and organize fitness and sports activities service
5. HUMAN RESOURCE SCALE
Office: 32 people
Technique: 42 people
Engineer: 8 people
6. THE OTHER ADVANTAGES
- The exclusive lawn products distributor of ACT Global Sports (USA)
- With the transfer of technology and the proprietary ASI (USA) agent, Nurteks (Turkey),
SALTEK (Finland), experts in the field of manufacturing and installation of artificial
grass.
- Exclusive agent for distribution of SMG (Federal Republic of Germany) products
specializes in manufacturing all kinds of machinery installation and maintenance of
artificial turf on the world.
- The product has been tested by LABOSPORT (France) international testing centers
certified quality standards achieved 1 Star and 2 Star FIFA in Vietnam.
II. ABOUT THE PROJECT:
La Khe football stadium project was built by An Hung urban construction investment
JSC. The project built on an area of 12,000 m2 (150mx80m) La Kha district, Ha Dong,
Hanoi. Currently, the land is still being used as a football stadium, but there are 04 types
of clay courtyard for 7 people, a parking area and a room for athlete to change clothes
and rest.
Page 3 of 17


Existing football pitch has deteriorated, the field is not flat but rough, poor drainage and
flooding often occurs when rain waterlogged. Area gravel parking lot, not convenient and
nice. The drinking water is too small and not enough to meet the number of people. Due
to the situation the number of customer is reduced when there are so many other stadiums
which are being put to use with modern equipment, qualified and very close to this area.
The current image of the field:

With the consent of the People's Committee of La Khe ward, Ha Dong District, Ha Noi,
An Hung urban construction Investment Co., Ltd. decides to upgrade the football stadium
to a new stadium under the FIFA standard artificial pitch. Qualify yard for 11 people with
the area of 105m x 68m, can be divided into 04 courtyards with an area of 34m x 52.5 m.
Ground has 20 surrounding lights columns, protective grid is 20 meters high. Modern
drainage system with 30cm wide drainage ditch running around the yard and into the
Page 4 of 17


general drainage system outside the region. Parking area is leveled. Rest area and a
revised roof steel framed houses 100m2 to sit outside for drinking. Image of the field
after construction:

III. EXECUTION PLAN
1. Structure work table:

Page 5 of 17


2. The detailed implementation plan:
a. Planning and construction of the infrastructure
Base infrastructure is constructed in accordance with construction standards of
international stadium, with standard drainage system put out water drain system
surrounding the stadium. Infrastructure platform is also designed to create a slope to
avoid the two sides to hold water.
 Task list
No

Previous task

Time

1.
2.

of people
Tilling (machine using)
02
Flattened
(machine 02

1

05 days
02 days

3.

using)
Drainage

2

03 days

Page 6 of 17

Task

Number

system 06


4.
5.

installation
Curb
Digging,

02
building 10

drainage

ditches.

3
3

01 days
05 days

6.

(machine using)
Base camp, creating a 04

3

01 days

7.
8.

slope
Grit
Compaction

6
7

01 days
01 days

04
(machine 02

using)
 Prioritize work chart

 Task details:
- Clean up, clean grass, trees, mulch layer. Use tillers and cultivators of the soil.
- Use 10 ~ 12 ton compactor roller at K = 0.9 ~ 0.95. Flattened 20cm thick layers,
in case water reclamation, vacuum up water then mud before leveling.
- Flattened ground slopes down to 0 %.
- Locate the field, drained location, the associated works such as canteen, toilet ...
Select a location for the airport for the best convenient drainage.

Page 7 of 17


- Use a brick card ( or brick ) to build a 100 ~ 200 thick, depending on the curb
height (usually 200mm ) below the concrete lining rocks or stones 1 4 × 6 × 2
M150 . The curb is higher than the lower surface 10cm.
- Develop drainage ditch about 25cm wide, 25cm high (the beginnings) with 0.2 %
slope ditches, cloth cover is 35cm wide, 50cm long cut 2 tops.
- Pour the rock 0 × 4, used turtles car split into small pile, use coral scraping off
layers. 0x4 ice thickness is 10cm (with high curb). Roller and leveled compacted.
Use stretch cord to test the flatness of the background. The slope of the rock 0 × 4
is 0 %
- Refill the sloped rock 0.5 ~ 0.6%, higher than the edge of the field between the
airport about 5 cm. Compaction. Also use strained wire to check the flatness and
the slope of the background. Rock volume of about 10 cm using.
- Sprinkle sand onto the 4cm, roller compaction to ensure waterproof down below.
b. Planning and construction of grass
 Task list
No
1.
2.
3.
4.
5.

Task

Number of Previous task

Time

Spread grass
Glue
Spread and hit the sand
Spread rubber particles
Construction goalposts

people
04
04
04
02
04

02 days
02 days
02 days
01 days
0.5 days

 Prioritize work chart

Page 8 of 17

1
2
3
3


 Task details:
- Check the lower side of the field to ensure the absolute surface flat, the slope
satisfactory (0.5% -0.6%).
- Cut, creating borders and white contour grass:
For the record straight: slitting knives, placed neatly and using file along the
road width 80mm
For curved border: slitting knives, compasses created strings lead back by radius,
then trimmed to create a 80mm wide rims fitted white grass
- Glue: Use the paintbrushes permeable glue to scan the 300mm wide Hiflex surface, 2
sides are pasted together, do the same to the white grassy. Done, use pads and fixed
subtitles sand and wait for the dry glue.
- After hitting and spreading sand: sand is spread on the grass layer about 2cm thick,
divided into several layers, can be spread by hand or machine sanding (Note: Must
prepare the clean floor, dry sand and must make grass background dry). Use a rake or
lawn machines hit the sand fell until about 2cm thick.
- Spread rubber particles: The rubber layer spread about 0.8 cm to 1 cm, an average of
6kg -8 kg/m2 of the artificial turf, can be laid by hand or by machine. Then use a lawn
rake or hitting machine for rubber granules dropped.

c. Planning and construction of lighting systems:
Page 9 of 17


 Task list
No
1.
2.

Task
Power

Number of people
line
02

installation
Lamppost

preparation
3.
Hole digging
4.
Buried column
5.
Wiring
 Prioritize work chart

Previous task

Time
01 day

10

1

01 day

02
10
02

1
2
3

01 day
01 day
01 day

 Task details:
- Lamppost: Lamp holder, just to get the ball screens by galvanized iron. Column has
bolts, screws, columns and lamp case. Number: 20 columns
- Headlights (lights): High-pressure lamps, with power of 1000W. Each head light has
2 lights. The number is 40 lights. Lights are mounted on the column while wearing
turnout.
- Buried hole of lamppost is 30x30 sizes, 1.5 m deep.
- After the buried, compaction. Construction of cement around 10cm each way. Bolted
from the lampposts feet of cement.
- Connect the power cord right after the installation of the column.
d. Protective planning and construction of net:
Page 10 of 17


 Task list
No
1.
2.

Task
Grid preparation
Digging holes to

Number of people
02
04

Previous task
1

Time
01 day
01 day

3.
4.
5.

burry pillars
Buried column
Building grid
Graft
grid,

04
04
04

2
3
3

01 day
01 day
01 day

completion
 Prioritize work chart

 Task details:
- Use outdoor nylon fiber grid with high durability. Fiber grid is 0.5cm.
- Hole buried is 20x20cm. Construct aluminum columns. Length of yard is 06 pipes
on each side; the width of yard is 02 pipes.
- Grid is mounted on lampposts
- The bottom is stretched
e. Planning and construction of parking lots:
 Task list
No
1.
2.
Page 11 of 17

Task
Tilling (Machine)
Rolling,

Number of people
Cultivators with the

background field
leveling, Along with doing

Previous task

Time

1

01 day


3.
4.
5.

compaction
field
Cemented
Checkered
Tension
protection

02
01
02

2
3
3

01 day
01 day
01 day

wire
 Prioritize work chart

 Task details:
- Tilling and roller leveling will be done with the first phase to ground infrastructure. Use
rollers flattened ground after cleaning and scarifying.
- Cemented to dry in 01 day to conduct a grid and checkered. Share location for
automobile and motorcycle, creating a convenient way to easily place the car.
f. Planning and construction of the beverage
 Task list
No

Task

Number of people

Previous

Time

task
1.
2.

Paint the house
Do the pitch

02
Along with

3.

Prepare materials for

parking ground
02

4.
5.

the steel frame
Aluminum framing
Insert the aluminum

Page 12 of 17

04
04

01 day
01 day

the
2

01 day

3
4

02 days
02 days


roof
 Prioritize work chart

 Task details:
- Specify color: gray paint, type: outdoor
- The yard is done with garage. (There has been the pre-cemented with 01 thin layer)
- Aluminum Frame mounting screws fixed to the yard
- Iron roof, anti-gust and fixed.

IV. BUDGET PLAN
No
I
1.
2.
3.

Expense
Infrastructure
Platform
Machine rental
Materials
Workers

Amount (VND)
220,000,000

Interpretation

40,000,000 Plows and rollers
150,000,000 Drainage materials, brick,
stone base, sand ...
30,000,000 Outsourcing, excluding the
company's experts

II
4.
5.
6.
Page 13 of 17

Grass
Artificial Grass
Other material
Workers

2,615,600,000
2,427,600,000 Price340,000VND/m2.
7140m2 yard
100,000,000 Rubber particles, sand ...
20,000,000 Outsourcing, excluding the


7.

company's experts
48,000,000 02 big goal frames and 08

Goal frame

small frames.
8.
III
9.
10.
11.
IV
12.
13.

Workers
The lighting system
Head lights
Light
Wires, other materials
Protection Grid
Column
Protection grid

20,000,000
38,760,000
80,000,000
40,000,000
5,000,000
125,000,000
8,000,000
20,760,000

02 head lights
40 lights of 1000W
Column: 16 aluminum pipes
6,920 m2 Unit price 3000
VND / 01 m2

14.
V
15.

Workers
Parking
Doing yard

16.

Protection Wire

10,000,000
0
0 Along with the yard
0 Expenditure

Management

Board
VI
17.
18.
19.
20.

The canteen
Paint
Cemented
The steel frame
Workers
Total
Estimated risk 10%
The total estimated

2,000,000
0 Do the same with car parks
30,000,000 The steel frame package
2,000,000
3,033,360,000
303,336,000
3,336,696,000

expense

V. PLAN CHECK, CONSTRUCTION SUPERVISION STATUS:
1. Project process chart: (See next page)

Page 14 of 17


Project control process: Construction of La Khe football stadium - Ha Dong

Page 15 of 17


Group Assignment – Project Management
2. Checklists and time:
No

Task

Implementation

Note

date
11/11/2013

All department

15/11/2013

Leveling

construction

20/11/2013

checking
Leveling

construction

5. Drainage construction checking 23/11/2013

checking
1st time

6. Canteen checking

Steel

1. Deployment meeting
2. Car-park yard checking
3. Background checking
4. Background checking

25/12/2013

frame

canteen

7. Drainage construction checking 25/11/2013

checking
Improving field drainage

8. Drainage construction checking 27/11/2013

Construction of irrigation

9. Drainage construction checking 02/12/2013

water
Improving

10. Pitch checking

06/12/2013

water
Spreader grass checking

11. Grid column checking

06/12/2013

Test holes dug to burry

06/12/2013

column
Test holes dug to burry

12. Lamppost checking

irrigation

column
13. Car-park completion checking

06/12/2013

14. Pitch completion checking

10/12/2013

15. Grid and lights checking

11/12/2013

16. Pitch checking

12/12/2013

Search out sanding

17. Pitch checking

13/12/2013

Rubber particles spreader

Glue checking

checking
Paris Graduate School of Management - PGSM

Page 16 of 17


Group Assignment – Project Management
18. Completion

References:
1. Curriculum: Project Management - Paris Graduate School of Management
2. Documentation for construction of artificial turf football field – Hoang Nguyen
Limited Company Website: http://hoangnguyensports.com.vn/
3. Project Management Software by Microsoft Project 2007.

Paris Graduate School of Management - PGSM

Page 17 of 17